Route 17/Exit 131 Reconstruction Project

Diagram of final form of new intersection of Routes 32 and 17

Final plan for new intersection

The NYS Department of Transportation has a Route 17/Exit 131 Construction Project website with the latest information and updates related to the project.

Current Update from DOT – 12/10/18

map of new construction traffic pattern

ROUTE 32

Traffic on Route 32 is scheduled to be shifted west onto the newly constructed roads and bridges during the week of December 17, 2018 (see graphic above). The number of lanes will remain the same and additional signage will be in place to guide motorists through the new traffic pattern. Please proceed through this area with care and observe the posted speed limits as there will be ongoing construction activities in this area over the coming months.

ROUTE 17

The left lane is a dedicated through-lane from Exit 130 eastbound to the NYS Thruway toll booths. Eastbound traffic on Route 17 will remain shifted onto the paved median to maintain a safe and unobstructed work zone. Local traffic should continue to use the right lane only as exits are not permitted from the left lane.

RAMPS

The Route 17 westbound ramp from Route 32 northbound will be relocated north of the Route 6 overpass (see graphic below). The new traffic pattern is expected to be in place during the week of December 17, 2018. Additional signage will be in place to guide travelers through the new traffic pattern.

map showing ramp pattern on route 32

 


Anticipated Project Timeline

Winter 2018 – Summer 2018

  • Traffic Changes & Impacts:
    • Relocate Existing Road Signs & Traffic Lights
  • Construction Site & Land Preparations:
    • Install Orange & Silt Fencing
    • Setup Equipment Staging Areas
    • Tree Clearing
    • Remove existing topsoil: Route 32, Route 17, Central Valley Elementary School, & Nininger Road
  • Temporary Construction:
    • Route 32 North Bound: Pavement for Lane Widening
    • Nininger Road: Pavement for Lane Widening
    • Route 17 Median: Pavement for Temporary Lane Shifts
  • Permanent Construction:
    • Route 32 Bridge over Route 17: Abutments & Center Pier
    • Utility Relocations: Route 32, Nininger Road, & Route 17
  • Traffic Changes & Impacts:
    • Route 32 Shifted onto Temporary Pavement
    • Route 17 Shifted onto Temporary Pavement
  • Permanent Construction:
    • Route 32 Southbound
    • Route 17 Eastbound: Right Lane & Shoulder
    • High School: Connector Road, Parking Lot D, & E
    • Park-N-Ride: 100 Vehicles (Staged Construction)

*Schedule subject to change. 


Public Information Meeting held on December 14, 2017

The state Department of Transportation held a public information meeting on Thursday, December 14 to explain the new design for its $150 million reconfiguration of Route 17′s Exit 131.

12/14/17 – Times Herald-Record story

12/28/17 – Photo News story

 

This page will be updated as information is made available.